Provision of new plates for existing switchboards, plant wiring. Rewriting of raw water purification sequences with existing devices and integration into existing automation.
Our role in the success of this project
- Survey of existing wiring and electrical design of the new plates
- Assembly and testing of the new plates and electromechanical components
- Collaboration with the electrician, the municipality's technical office and the plant operator
- Disposal of old plates, installation of new ones
- On-site cabling - quickly and without interruption of the water supply
- Relocation of the command and control station (ergonomics)
- Survey of operating sequences and drafting of new software
- Addition of a PLC periphery, integration into existing PLC and SCADA programmes
- Function check with the operator, optimisation of sequences